The first section will span 55 kilometres between Lingen and Bad Bentheim.
Nowega GmbH (DE56) is commissioning the first section of its hydrogen network

With 55 kilometres of hydrogen pipelines, transmission system operator Nowega GmbH (DE56) is commissioning the first section of its hydrogen network. In Nordhorn, the initial filling of the pipeline between Lingen and Bad Bentheim with hydrogen was initiated. The section in south-west Lower Saxony is a first part of the hydrogen core network and consists of 95 percent existing pipelines being converted for hydrogen transport. As part of the GET H2 network, the network section from Lingen to Bad Bentheim creates important connection opportunities for producers and users of climate-friendly hydrogen. 

 

Link to IPCEI Hy2Infra, Workstream 2 “Hydrogen Transmission Infrastructure”

 